• SCHOOL FACILITIES REFERENDUM 
     
    Anticipated Project Timeline 
  • Project #01 – Partial Roofing Project

    Design and documentation: target completion by end of April 2015

    Anticipated bidding period: +/-May 2015

    Target construction completion: by September 2015

     

    Project #02 – Interior/Exterior Renovations Project

    Design and documentation: target completion by end of July 2015

    Anticipated bidding period: +/-August 2015

    Target construction completion: by September 2016

     

    Project #03 –HVAC Upgrades Project

    Design and documentation: target completion by October 2015

    Anticipated bidding period: +/-November-December 2015

    Target construction completion: by September 2016

     

    Project #04 – Boiler Replacement Project

    Design and documentation: target completion by May 2015

    Anticipated bidding period: +/- May-June 2015

    Target construction completion: by October 2015