SCHOOL FACILITIES REFERENDUMAnticipated Project Timeline
-
Project #01 – Partial Roofing Project
Design and documentation: target completion by end of April 2015
Anticipated bidding period: +/-May 2015
Target construction completion: by September 2015
Project #02 – Interior/Exterior Renovations Project
Design and documentation: target completion by end of July 2015
Anticipated bidding period: +/-August 2015
Target construction completion: by September 2016
Project #03 –HVAC Upgrades Project
Design and documentation: target completion by October 2015
Anticipated bidding period: +/-November-December 2015
Target construction completion: by September 2016
Project #04 – Boiler Replacement Project
Design and documentation: target completion by May 2015
Anticipated bidding period: +/- May-June 2015
Target construction completion: by October 2015